Prime cost

In one sentenceThe sum of a product's direct materials and direct labor, meaning its cost before manufacturing overhead is added.

Simply put

It is the part you can calculate accurately for each product: the materials that went into it and the work the workers did on it directly.

Adding manufacturing overhead to it gives you the full production cost per unit.

Worked example

A furniture workshop makes a chair that needs direct materials of 30 SAR and direct labor of 15 SAR, and it is charged 10 SAR of overhead.

Direct materials30 SAR
Direct labor15 SAR
For comparison: full production cost = 45 + 10 overhead55 SAR
Prime cost = 30 + 1545 SAR

Formula: Direct materials + Direct labor